Short answer

A change order records three things that the people who sign it have agreed on: the change in the work, the adjustment (if any) to the contract sum, and the adjustment (if any) to the contract time. AIA A201-2017, Section 7.2.1, lists those three items, and AIA's instructions for the G701-2017 form ask for a detailed description of the change with supporting exhibits, the contract sum history, and the change in days along with the new substantial completion date. Before you price anything, find your contract's notice clock. Under A201-2017, claims must be started within 21 days and concealed conditions reported within 14 days. Under FAR 52.243-4, costs incurred more than 20 days before written notice of a constructive change can't be recovered, and you have 30 days to assert your adjustment. This is general information, not legal advice. Check your own contract and talk to a construction attorney.

In this article

    A change order is the paperwork that makes a change in scope, price, or time binding. A weak one can turn into a dispute that lasts longer than the work did. This post covers how to write one that a reviewer can approve: what the standard forms and the federal changes clause actually require, the notice clocks you have to beat before you price anything, and a worked example of the contract sum math.

    This is general information, not legal advice. Contract forms are routinely modified, and the clauses in your contract govern your project, not the standard forms summarized here. Read your own agreement, general conditions, and supplementary conditions, and talk to a construction attorney before you rely on any deadline or entitlement below.

    It is written for general contractors and for self-perform trades, such as excavation, concrete, and utilities, that write change order proposals to a GC or an owner.

    Three different instruments, and why it matters which one you are holding

    AIA A201-2017, General Conditions of the Contract for Construction, provides three ways to change the work after the contract is signed (Section 7.1.1): a change order, a construction change directive, or an order for a minor change in the work. Section 7.1.2 sets out who has to agree to each:

    Instrument (A201-2017) Who signs or agrees What it does
    Change order (§ 7.2) Owner, contractor, and architect Records agreement on the change in the work, the contract sum adjustment, and the contract time adjustment
    Construction change directive (§ 7.3) Owner and architect; contractor may or may not agree Directs the change before price and/or time are agreed; used “in the absence of total agreement on the terms of a Change Order”
    Minor change (§ 7.4) Architect, in writing A change consistent with the intent of the documents that involves no adjustment to sum or time

    ConsensusDocs uses different names. ConsensusDocs 202 is its change order form. ConsensusDocs describes the form as documenting agreed adjustments to scope, schedule, and contract price, signed by both parties. ConsensusDocs 203, the interim directive, lets the owner order the constructor to proceed when no change order has been agreed. In its September 2023 summary of contract updates, ConsensusDocs says the term “interim directive” covers directed changes ordered because the parties have not agreed on cost and schedule impacts, as well as field instructions. It also says AIA’s construction change directive is “a similar concept,” and that issuing an interim directive does not necessarily increase price or time.

    On federal fixed-price construction, FAR 52.243-4, Changes (June 2007), works differently again. The contracting officer may issue a written change order within the general scope of the contract (paragraph (a)). Under paragraph (b), any other written or oral order, including a direction, instruction, interpretation, or determination, that causes a change is treated as a change order, but only if the contractor gives written notice stating the date, circumstances, and source of the order, and that it regards the order as a change order.

    The practical point: before you write anything, know whether you are pricing an agreed change, responding to a directive you haven’t agreed to price, or giving notice that something you were told to do is a change. Each one is a different document.

    The minor-change trap

    A201-2017 Section 7.4 says that if you believe a minor-change order will affect the contract sum or time, you must notify the architect and not proceed. If you perform the work without that notice, you waive the adjustment. A self-perform crew that “just does it” because the field order looked small can lose the change.

    Find your notice clock first

    Price later. Notice first. These are the clocks in the documents opened for this post. Your contract may shorten, lengthen, or replace every one of them.

    Source Trigger Clock
    A201-2017 § 15.1.3.1 A claim, including a claim for the cost or time of a change Within 21 days after the event, or within 21 days after you first recognize the condition, whichever is later
    A201-2017 § 3.7.4 Concealed or unknown site conditions Notice before the conditions are disturbed, and no later than 14 days after first observing them
    A201-2017 § 7.4 An architect’s minor-change order that you believe affects sum or time Notify the architect and don’t proceed
    FAR 52.243-4(d) Constructive change under paragraph (b) Except for defective specifications, no adjustment for costs incurred more than 20 days before your written notice
    FAR 52.243-4(e) Any change under (a) or (b) Assert your right to an adjustment within 30 days, unless the Government extends the period. The clause prescription says agencies may vary the 30 days.
    FAR 52.236-2 (Apr 1984) Differing site conditions on a federal job Written notice “promptly, and before the conditions are disturbed”

    Two federal caveats:

    • The FAR is being rewritten. The text above is the codified FAR at acquisition.gov (FAC 2026-01, effective March 13, 2026). Under the Revolutionary FAR Overhaul, agencies are issuing class deviations that use model deviation text. The model deviation text of 52.243-4 that we read is reorganized, but it keeps the same 20-day cost limit and 30-day assertion period. The model deviation text of 52.236-2 drops the sentence letting the contracting officer extend the notice period. Your contract contains whichever version the agency inserted, so read the clause in your contract.
    • Federal rules also have a claims process with its own requirements. This post doesn’t cover it.

    What the change order has to say

    A201-2017 Section 7.2.1 defines a change order as a written instrument, prepared by the architect and signed by the owner, contractor, and architect, that states their agreement on:

    1. the change in the work,
    2. the amount of the adjustment, if any, in the contract sum, and
    3. the extent of the adjustment, if any, in the contract time.

    AIA’s published instructions for G701-2017, Change Order, describe what goes in each part of the form:

    • Description of the change. A detailed description, or references to exhibits that describe the change in detail, including any drawings, specifications, documents, or other supporting data that clarify the scope.
    • Determination of costs. The original contract sum (or GMP); the net change from previously authorized change orders; the sum before this change order; the increase or decrease; and the new contract sum. The instructions note that the net change from prior change orders does not include construction change directive amounts, unless the contractor later agreed to them and they were recorded as a change order.
    • Change in contract time. The increase or decrease in days, and the date of substantial completion including this adjustment.
    • Execution. The parties execute G701 when the owner and contractor, with the architect’s concurrence, have agreed on the change, including the adjustments to sum and time.

    The G701 form text is copyrighted, and AIA’s instructions say it may not be reproduced without permission. This post describes the fields. It doesn’t copy the form.

    Even if your project uses ConsensusDocs, a GC’s own form, or a federal contract modification, the same three items apply. A reviewer approves a document that clearly states what changed, what it costs, and what it does to the schedule.

    How to write the proposal, step by step

    1. Name the trigger document

    Start by citing what started the change: an owner request, an architect’s supplemental instruction, a construction change directive or interim directive, an RFI response, a field directive, a differing site condition, or a code official’s correction. Give the date, the author, and the document number. Under FAR 52.243-4(b), “the date, circumstances, and source of the order” is the notice content the clause requires. It is also a good habit on private work.

    2. Describe the scope as in and out

    Write the scope so that someone who wasn’t at the meeting can price it. Include:

    • the drawing sheets, details, and specification sections affected, by number;
    • quantities, with units and how you measured them;
    • what is included, such as demo, disposal, testing, and protection of adjacent work;
    • what is excluded or reserved, such as unknown conditions behind the work, a related schedule impact you will price separately, or permit fees by others.

    If the change came from an RFI answer, quote the answer word for word and attach it.

    3. Price it on the basis the contract allows

    A201-2017 Section 7.3.3 lists the methods for adjusting the contract sum under a construction change directive:

    • a lump sum, properly itemized and supported by enough data to evaluate it;
    • unit prices stated in the contract or agreed later;
    • cost determined in an agreed way, plus a mutually acceptable fixed or percentage fee; or
    • the architect’s determination under Section 7.3.4.

    Section 7.3.4 says that if the contractor doesn’t respond promptly or disagrees with the method, the architect determines the adjustment from reasonable expenditures and savings, plus the overhead and profit set out in the Agreement, or a reasonable amount if the Agreement doesn’t set one. Unless the contract documents say otherwise, Section 7.3.4 limits costs to five categories:

    • labor costs, including applicable payroll taxes, fringe benefits, workers’ compensation, and other approved employee costs;
    • materials, supplies, and equipment, including transportation;
    • rental of machinery and equipment, excluding hand tools;
    • bond and insurance premiums, permit fees, and sales or use taxes directly related to the change;
    • supervision and field-office personnel directly attributable to the change.

    Even when you are pricing a lump-sum proposal for agreement and no directive has been issued, organizing your backup in those categories gives the architect what they need to evaluate it. Use the markup percentages your contract states. This post doesn’t suggest any. Our companion post, How to Price a Change Order: Markups You’re Actually Entitled To, covers the cost buildup in more detail.

    4. Price time separately

    State the change in calendar days and the new substantial completion date, which are the two time entries the G701 instructions describe. A201-2017 Section 8.1.4 says “day” means calendar day unless the contract defines it otherwise. If you can’t yet determine the time impact, say so explicitly and reserve it. Don’t leave the time field blank, because a blank may read as zero.

    5. Watch the credits

    A201-2017 Section 7.3.8 has two rules:

    • A deletion or change that results in a net decrease in the contract sum is credited at actual net cost, as confirmed by the architect.
    • When a change involves both additions and credits for related work or substitutions, overhead and profit are figured on the net increase, if any.

    That second rule changes the math, as the example below shows.

    6. Track the signature path

    A change order isn’t a change order until the people who must agree have signed it. Under A201-2017 those are the owner, contractor, and architect. Under ConsensusDocs 202, ConsensusDocs says both parties, typically the owner and contractor, sign. Under the FAR, the contract is modified in writing by the contracting officer. Until then, log it as a pending item, not as revenue.

    Worked example: the contract sum math

    All of the numbers below are assumptions chosen to illustrate the arithmetic. They aren’t typical costs.

    Assumed contract history:

    • Original contract sum: $1,250,000
    • Net change from previously executed change orders: +$38,400
    • One construction change directive, priced by the contractor at $12,000 but not yet agreed or recorded as a change order

    Assumed change: A footing detail is revised, which adds work with a direct cost of $9,400 and deletes related work with a direct cost of $3,100.

    Step 1: net direct cost. $9,400 − $3,100 = $6,300.

    Step 2: overhead and profit on the net, per A201-2017 § 7.3.8. If your Agreement states a combined overhead-and-profit rate P, the allowance is P × $6,300, not P × $9,400. This example leaves P blank because the rate comes from your contract, not from this post. Say the contract rate produces an allowance of $X. The change order amount is then $6,300 + $X, plus any other items your contract allows, such as bond premium.

    Step 3: carry it on the G701-style summary. To keep the arithmetic checkable, assume the agreed change order amount is +$7,000:

    Line Amount
    Original contract sum $1,250,000
    Net change by previously authorized change orders +$38,400
    Contract sum prior to this change order $1,288,400
    Increase by this change order +$7,000
    New contract sum $1,295,400

    Check: $1,250,000 + $38,400 = $1,288,400, and $1,288,400 + $7,000 = $1,295,400.

    The $12,000 directive is not in the “previously authorized” line. AIA’s G701 instructions exclude construction change directive amounts until they are agreed and recorded as a change order. A201-2017 Section 7.3.9 lets the contractor request payment for directive work in pay applications, based on the architect’s interim determination, while the price is still open. Track it on its own line in your change log.

    An RFI answer is not automatically a change order

    Contractors often treat an RFI response as an approval to bill. The documents don’t treat it that way.

    • A201-2017 § 3.2.4. If the contractor believes that clarifications or instructions issued in response to its RFIs involve added cost or time, the contractor submits a claim under Article 15. The response alone doesn’t adjust the contract.
    • A201-2017 § 4.2.14. The architect responds to RFIs in writing, within any agreed time limits or otherwise with reasonable promptness, and may issue supplemental drawings and specifications. Neither of those is a change order.
    • FAR 52.243-4(b). An “interpretation” from the contracting officer that causes a change is treated as a change order only if you give the written notice the paragraph requires. Paragraph (d) limits your costs to the 20 days before that notice, except for defective specifications.

    When an RFI answer changes your work, send notice within your contract’s window, then write the change order proposal. Our post How to Write an RFI to Get Answers has examples of RFIs that flag cost before the answer arrives.

    Common reasons change order proposals stall

    • No trigger document. “Owner asked for it” with no name, date, or written direction.
    • Scope that only the estimator understands. No sheet references, no quantities, no exclusions.
    • Unsupported lump sums. A201-2017 Section 7.3.3 calls for a lump sum that is “properly itemized and supported by sufficient substantiating data to permit evaluation.”
    • Markup on the gross. Applying overhead and profit to additions while ignoring the related credits, contrary to Section 7.3.8 when A201 governs.
    • Time left blank or unexplained.
    • Late notice. No proposal, however well written, fixes a missed notice deadline that your contract enforces.

    For the lifecycle after the proposal goes out, including logging, aging, and the proceed-on-verbal problem, see Change Order Management: Capture, Price & Approve Work Without Leaking Margin.

    Before you send it

    1. Has notice gone out within your contract’s clock?
    2. Does the proposal cite the trigger document by date, author, and number?
    3. Is the scope written as in and out, with sheet and spec references and quantities?
    4. Is the price organized on the basis your contract allows, with backup?
    5. Is markup at the contract rate, and on the net where additions and credits are related?
    6. Are days and the new substantial completion date stated, or explicitly reserved?
    7. Does the contract sum summary reconcile, with directives kept separate?
    8. Do you know who has to sign it?

    Again, this is general information, not legal advice. Your contract and a construction attorney are the authorities on your project.

    Sources

    Sources that could not be verified for this draft

    • The full, current text of ConsensusDocs 200, 202, and 203. These are paid documents. Only ConsensusDocs’ public catalog and news pages were read, and no ConsensusDocs section numbers are cited here.
    • EJCDC change order documents, which weren’t opened.
    • AIA A201 sections that are missing from the public sample. The sample skips some pages. Only the sections listed above were read.
    • Any particular agency’s FAR Overhaul class deviation. Check your contract for the version of 52.243-4 and 52.236-2 it includes.

    Frequently asked questions

    What should a construction change order include?

    Under AIA A201-2017 Section 7.2.1, a change order states the parties' agreement on the change in the work, the amount of any adjustment to the contract sum, and the extent of any adjustment to the contract time. AIA's G701-2017 instructions add a detailed description with exhibits, the original contract sum, the net change from prior change orders, the sum before this change order, the increase or decrease, the new sum, the change in days, and the new substantial completion date.

    What is the difference between a change order and a construction change directive?

    In A201-2017, a change order is signed by the owner, contractor, and architect and records full agreement. A construction change directive is signed by the owner and architect, directs the change before price or time is agreed, and is used when there is no total agreement on a change order. ConsensusDocs uses the term interim directive (ConsensusDocs 203) for a similar idea.

    Is an RFI response a change order?

    Not by itself. A201-2017 Section 3.2.4 says that if the contractor believes an RFI response involves added cost or time, the contractor submits a claim under Article 15. Under FAR 52.243-4(b), an interpretation or direction counts as a change only if the contractor gives written notice that it regards the order as a change.

    How long do I have to give notice of a change on a federal job?

    Under FAR 52.243-4 (June 2007), you can't recover costs incurred more than 20 days before your written notice of a constructive change, except costs from defective specifications. You must assert your right to an adjustment within 30 days, a period the Government can extend and that the clause prescription lets agencies vary. Check which version of the clause, including any FAR Overhaul deviation text, is actually in your contract.

    What markup can I put on a change order?

    Whatever your contract allows. A201-2017 Section 7.3.4 uses the overhead and profit set out in the Agreement, or a reasonable amount if the Agreement doesn't state one. Section 7.3.8 says that when a change has both additions and credits, the overhead and profit allowance is figured on the net increase. This post doesn't suggest a percentage.

    General contractors and every self-perform trade — pool, framing, concrete, electrical, plumbing, HVAC, landscape, heavy civil, and the trades between them.

    Next read

    how to write a change orderhow to write a change order in constructionhow to write a change order proposalconstruction change orderchange order vs construction change directiveFAR 52.243-4 changes clause